Data Center Fiber Design No fiber jumpers shall run between the Data Center (321) and the Data Center IDF (322). All fiber from the Data Center cabinets to the Data Center racks is 50 micron. Following is the CNS fiber installed into Data Center and Data Center IDF:
When CCS needs fiber connectivity to the Data Center IDF, they will submit a shopping cart order. CNS will install fiber jumpers from our equipment to Rack 322-03-01, FIC# 819 and notify CCS of the Fiber pair activated. CCS will be responsible for purchasing and installing fiber jumpers from FIC# 819 in Rack 321-37-01 to the Data Center 50 Micron termination racks, as well as the jumper in the cabinet to their equipment. Any connectivity out of the building that does not go through the Data Center IDF equipment will need to be designed/discussed on a case by case basis.